Still searching the internet aimlessly for PK0-004 materials you can trust? End the hunt at TestInsides: 797 expert-verified Q&As covering the CompTIA Project+ Certification objectives give you one reliable place to prepare instead of a dozen questionable tabs.
CompTIA PK0-004 Exam Overview:
| Certification Vendor: | CompTIA |
|---|---|
| Exam Name: | CompTIA Project+ Certification Exam |
| Exam Number: | PK0-004 |
| Exam Price: | USD ≈ 358 (may vary by region and test center) |
| Available Languages: | English |
| Exam Format: | Multiple Choice, Multiple Response |
| Certificate Validity Period: | No fixed validity; CompTIA recommends staying current with exam updates and may require continuing education to maintain certification relevance |
| Related Certifications: | CompTIA Project+ (PK0-005) |
| Real Exam Qty: | Maximum of 95 |
| Exam Duration: | 90 minutes |
| Passing Score: | 710 (on a scale of 100–900) |
| Sample Questions: | ![]() |
| Exam Way: | Delivered through Pearson VUE test centers and CompTIA's authorized testing channels. |
| Pre Condition: | No formal prerequisite exam required; recommended 12 months of project management experience or equivalent practical application. |
| Official Syllabus URL: | https://www.comptia.org/en/certifications/project |
CompTIA PK0-004 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Project Tools & Documentation | 21% | - Tools and Documentation Skills
|
| Project Basics | 36% | - Fundamental Project Concepts
|
| Project Constraints | 17% | - Managing Constraints and Risk
|
| Communication & Change Management | 26% | - Communication Methods and Change Control
|
PK0-004 Exam Essentials: Format, Topics, and Policies
The current exam information lists Maximum of 95 questions for the PK0-004 exam, with 90 minutes minutes allowed. Practicing against the clock at home builds the pacing habits that exam day rewards.
The CompTIA Project+ Certification blueprint covers these main domains:
- Project Constraints (17%)
- Project Tools & Documentation (21%)
- Project Basics (36%)
Additional domains complete the official outline, and our bank covers the full range.
Your money is protected by clear conditions. If you fail the corresponding exam within 60 days of purchase, send us a scanned copy of your enrollment slip and your official Score Report PDF within two days of the exam date; verified claims receive a full refund within seven days. The exclusions: exams taken within three days of purchase, a candidate name that does not match the payer, and free or expired products. If you prefer, we can exchange your product for two others of equal value instead.
CompTIA lists the following prerequisites for the CompTIA Project+ Certification: No formal prerequisite exam required; recommended 12 months of project management experience or equivalent practical application..
Check the official certification page for the latest requirements before booking.
Because we remove the guesswork at every step. The PK0-004 bank consolidates the CompTIA Project+ Certification knowledge points into expert-verified Q&As instead of leaving you to sift through the internet alone. A free demo shows the quality before you buy; instant delivery starts you the minute you do; 365 days of free updates — with a notification each time a new version releases — keep you current; and a strict information safety system plus a 7/24 golden-standard support team protect you throughout.
As of the latest information, the PK0-004 exam requires a score of 710 (on a scale of 100–900) to pass, and registration costs USD ≈ 358 (may vary by region and test center). CompTIA sets both figures, so verify them on the official site when you book.
Upon successful payment, our system automatically emails the product to your mailbox and shows an instant download link — delivery typically takes about a minute. If nothing arrives within two hours, check your spam folder first, then contact our 7/24 support team. Installations are unlimited. Your purchase also includes 365 days of free updates: whenever we release a new version, we notify you to download it — no need to wait or worry about validity — and a 50% renewal discount applies when the period ends.
CompTIA Project+ Certification Sample Questions:
Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?
- A. Instant messaging to the project coordinator and project scheduler
- B. Email and instant messaging to project team members and the project team members and the project sponsor
- C. Video conferences with key stakeholders and the project champion
- D. Text messages to and voice conferences with all stakeholders and project team members
Correct Answer: C 🗳️
Project A is delivering the foundation for Project B.
Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer.
Which of the following is the MOST likely impact to Project B?
- A. The cost will increase.
- B. The schedule will change.
- C. There will be no impact.
- D. The scope will change.
Correct Answer: B 🗳️
A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?
- A. Three
- B. Zero
- C. One
- D. Two
Correct Answer: A 🗳️
A stakeholder tells the project manager that a vendor was verbally aggressive during a meeting. Since the project is almost completed, the project manager decides to log and close the issue. Which of the following strategies does this represent?
- A. Confronting
- B. Compromising
- C. Forcing
- D. Smoothing
Correct Answer: C 🗳️
A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:
- A. scope statements and issue log
- B. project dashboard and status report
- C. project management plan
- D. action items and meeting minutes
Correct Answer: A 🗳️