NEW QUESTION 27
Which estimation technique can be used in to size the User Stories during Sprint Planning?
Please choose the correct answer.
Response:

  • A. Detailed bottom-up effort estimate that breaks each User Story up into hours or shorter tasks
  • B. Detailed bottom-up effort estimate by the Scrum Master in Story Points based on the User Story complexity
  • C. Relative estimate in Ideal Person Days that reflects the best estimate provided by the project team
  • D. Product Owner's relative estimate of the effort that will be needed to implement the User Story

Answer: D

 

NEW QUESTION 28
In which phase should you first run the SAP Readiness Check for SAP S/4HANA in a "Selective Data Transition" transition path, in a System Consolidation scenario that includes conversion from SAP ERP?
Please choose the correct answer.
Response:

  • A. Prepare
  • B. Discover
  • C. Explore
  • D. Realize

Answer: B

 

NEW QUESTION 29
In Which phase does the Transition to Operations work stream start?
Please choose the correct answer.
Response:

  • A. Prepare
  • B. Realize
  • C. Deploy
  • D. Explore

Answer: B

 

NEW QUESTION 30
What are some of the key characteristics of the implementation approach in SAP Activate Methodology?
There are 3 correct answers to this question.
Response:

  • A. Delta-based
  • B. Fixed scope
  • C. Cloud Ready
  • D. Based on Ready-to-use Content
  • E. On premise only

Answer: A,C,D

 

NEW QUESTION 31
Which accelerators support the Fit-to-standard workshop in the Explore phase?
There are 2 correct answers to this question.
Response:

  • A. Test Strategy
  • B. Business-Driven Configuration Questionnaire
  • C. Quality Gate Checklist
  • D. Backlog template

Answer: B,D

 

NEW QUESTION 32
What is the purpose of the scrumboard?
Please choose the correct answer.
Response:

  • A. To document the results of integration testing
  • B. To show the functional breakdown of the solution scope
  • C. To manage the resource load
  • D. To visualize team progress

Answer: D

 

NEW QUESTION 33
How can SRCUM teams be organized?
Please choose the correct answer.
Response:

  • A. By project phase
  • B. By work stream
  • C. By job title
  • D. By project governance level

Answer: B

 

NEW QUESTION 34
What are the three pillars of SAP Activate?
There are 3 correct answers to this question.
Response:

  • A. SAP Best Practices
  • B. Guided Configuration
  • C. SAP Solution Manager
  • D. SAP S/4HANA in-memory database
  • E. SAP Activate Methodology

Answer: A,B,E

 

NEW QUESTION 35
What technique helps a Scrum Team to prioritize a large, flat Backlog?
Please choose the correct answer.
Response:

  • A. Planning Poker
  • B. Fit/Gap Analysis
  • C. Retrospective
  • D. User Story Mapping

Answer: D

 

NEW QUESTION 36
In which phase do you create a prioritized list of user requirements?
Please choose the correct answer.
Response:

  • A. Prepare
  • B. Deploy
  • C. Explore
  • D. Realize

Answer: C

 

NEW QUESTION 37
Which of the following are levels in the structure of an SAP Best Practices Solution Package?
There are 2 correct answers to this question.
Response:

  • A. Building Blocks
  • B. Business Process Scenarios
  • C. Scope Items
  • D. Configuration Guides

Answer: A,C

 

NEW QUESTION 38
Which artifacts in the Testing work stream are created within the Realize phase for the New Implementation of SAP S/4HANA Cloud" transition path?
There are 2 correct answers to this question.
Response:

  • A. Functional Test Scenarios
  • B. Reporting Functional Specifications
  • C. User Acceptance Test - Plan
  • D. Functional Specifications

Answer: A,C

 

NEW QUESTION 39
Which of the following will help you avoid modification of standard functionality in SAP S/4HANA Cloud, Single Tenant Edit on?
There are 3 correct answers to this question.
Response:

  • A. SAP Code Inspector
  • B. Contract restrictions in SAP HANA Enterprise Cloud and SAP S/4HANA Cloud, Single Tenant Edition
  • C. The Side-by-Side Extensibility Option (such as SAP Cloud Platform)
  • D. A developer key
  • E. The 5 Golden Rules

Answer: B,C,E

 

NEW QUESTION 40
SAP now offers the ability to deploy and manage solutions in which of the following environments?
Please choose the correct answer.
Response:

  • A. On-premise
  • B. Cloud and On-premise
  • C. Cloud, On-premise and Hybrid
  • D. Cloud

Answer: C

 

NEW QUESTION 41
What information does the product team need so that they can estimate the relative size of backlog user story correctly?
Please choose the correct answer.
Response:

  • A. Definition of Done
  • B. Test strategy
  • C. Overall project schedule
  • D. Available project resources

Answer: A

 

NEW QUESTION 42
How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
Response:

  • A. Register on SAP Service Marketplace
  • B. Submit e-mail address via on-line form
  • C. Join SAP S/4HANA group on SAP Community Network
  • D. Send e-mail to SAP contact address

Answer: B

 

NEW QUESTION 43
Which of the following activities support the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition?
There are 2 correct answers to this question.
Response:

  • A. Non-production systems migration
  • B. Value determination
  • C. Data aging configuration
  • D. Custom code Adjustment planning

Answer: A,C

 

NEW QUESTION 44
What is a benefit of using Guided Configuration instead of the Implementation Guide?
Please choose the correct answer.
Response:

  • A. It ensures SAP updates do NOT conflict with customer configurations
  • B. It ensures configuration is done using SAP Solution Manager
  • C. It eliminates the need for Content Lifecycle Management
  • D. It eliminates the need to generate transport requests for configuration settings

Answer: A

 

NEW QUESTION 45
Which content packages are available in the SAP Package Library?
There are 2 correct answers to this question.
Response:

  • A. SAP Best Practices
  • B. SAP Activate Methodology
  • C. Rapid Deployment Solutions
  • D. Solution Builder

Answer: A,C

 

NEW QUESTION 46
How would you describe the Realize phase in the "New Implementation of SAP S/4HANA" transition path?
Please choose the correct answer.
Response:

  • A. Configuration copy
  • B. Configure and develop
  • C. Configure
  • D. Configure and adjust custom code

Answer: C

 

NEW QUESTION 47
......