NEW QUESTION # 21
What is one benefit of Program Increment (PI) Planning?
- A. It builds the social network on which the ART depends
- B. It creates the Vision and Roadmap
- C. It provides the opportunity to fully define the system architecture
- D. It helps define Program Management Review agenda
Answer: A
Explanation:
Explanation
One benefit of Program Increment (PI) Planning is that it builds the social network on which the Agile Release Train (ART) depends1. PI planning is a face-to-face event that establishes communication and collaboration among all team members and stakeholders2. It fosters a sense of shared mission and vision, trust and respect, and collective ownership and accountability3. It also helps to create a culture of learning and innovation within the ART4.
1: PI Planning - Scaled Agile Framework 2: The Ultimate Guide to PI Planning [2023 SAFe Edition] - Easy Agile 3: Program Increment (PI) is the Heart of Scaled Agile Framework (SAFe) 4: PI Planning - Scaled Agile Framework
NEW QUESTION # 22
Toward the end of the Iteration, the Product Owner raises a red flag stating there is an additional requirement that needs to be added to the current Iteration. The Agile Team could handle the requirement if they work late and over the next weekend. What should the Scrum Master do?
- A. Talk to the Product Owner, compare the new work to existing backlog priorities, and negotiate a sustainable solution
- B. Accept the work and extend the Iteration, informing other teams about the delay in delivery of other committed stories
- C. Meet with the team and if they agree to work overtime, accept the work
- D. Refuse the new requirement because it is too late to accept requirements at this point in the Iteration
Answer: A
Explanation:
Explanation
According to the Scrum Master article on the Scaled Agile Framework website, the Scrum Master should talk to the Product Owner, compare the new work to existing backlog priorities, and negotiate a sustainable solution when the Product Owner raises a red flag stating there is an additional requirement that needs to be added to the current Iteration. The article states that "The Scrum Master helps the Product Owner manage the backlog effectively by facilitating backlog refinement and prioritization. The Scrum Master also helps the Product Owner understand and apply the concepts of WSJF, MVP, MMF, and other economic prioritization methods. The Scrum Master supports the Product Owner in negotiating with stakeholders, customers, and the team to ensure that the backlog items are clear, concise, and ready for implementation." Therefore, the correct answer is B, talk to the Product Owner, compare the new work to existing backlog priorities, and negotiate a sustainable solution. The other options are not accurate, as they do not follow the Scrum principles of self-organization, time-boxing, and delivering value. Meeting with the team and accepting the work if they agree to work overtime (A) would violate the team's autonomy and sustainability. Accepting the work and extending the Iteration would disrupt the cadence and synchronization of the team and the ART. Refusing the new requirement (D) would ignore the feedback and collaboration of the Product Owner and the stakeholders.
NEW QUESTION # 23
Which statement is true about Lean-Agile development and contracting?
- A. Lean-Agile development contracts eliminate change orders
- B. Quality is built-in through collaboration and automation
- C. Lean-Agile development cannot be acquired with a fixed price contract
- D. They are based on a foundation of compliance
Answer: B
Explanation:
Explanation
The true statement about Lean-Agile development and contracting is A. Quality is built-in through collaboration and automation. Lean-Agile development is an iterative and incremental approach to software development that emphasizes flexibility, adaptability, and continuous improvement. Quality is not something that is added at the end of the development cycle, but rather something that is embedded throughout the process. Lean-Agile teams collaborate with customers and stakeholders to define clear and testable acceptance criteria for each work item. They also use automation tools to perform frequent testing, integration, and deployment of the software, ensuring that the solution meets the quality standards and compliance requirements12.
1: Advanced Topic - Agile Contracts - Scaled Agile Framework 2: Government - Building in Quality and Compliance - Scaled Agile Framework
NEW QUESTION # 24
Which three are configurations of SAFe 5.0? (Choose three.)
- A. Portfolio SAFe
- B. Multi-train SAFe
- C. Essential SAFe
- D. Full SAFe
- E. Lean Enterprise SAFe
- F. Team SAFe
Answer: A,C,D
Explanation:
Explanation
According to the SAFe 5 for Lean Enterprises article on the Scaled Agile Framework website, the three configurations of SAFe 5.0 are Essential SAFe, Portfolio SAFe, and Full SAFe. The article states that "SAFe 5 for Lean Enterprises is a knowledge base of proven, integrated principles, practices, and competencies for Lean, Agile, and DevOps. It's configurable and scalable for a single team, a large program, a portfolio, or an entire enterprise. SAFe 5 for Lean Enterprises is available in three configurations: Essential SAFe, Portfolio SAFe, and Full SAFe." Therefore, the correct answers are A, Essential SAFe, B, Portfolio SAFe, and E, Full SAFe. The other options are not accurate, as they are not the configurations of SAFe 5.0. Team SAFe is not a configuration, but a level within the Essential SAFe configuration. Multi-train SAFe (D) is not a configuration, but a term that refers to multiple Agile Release Trains (ARTs) working together. Lean Enterprise SAFe (F) is not a configuration, but a goal that SAFe 5.0 aims to help organizations achieve.
NEW QUESTION # 25
An agency performs development using contractors. Who is responsible for designating a story as 'Complete' based on acceptance criteria?
- A. The government Product Owner
- B. The government contracting officer
- C. The team
- D. The vendor program manager
Answer: A
Explanation:
Explanation
The government Product Owner is responsible for designating a story as 'Complete' based on acceptance criteria1. The Product Owner is the primary representative of the customer and stakeholder needs, and has the authority to accept or reject the work done by the team2. The Product Owner reviews the acceptance criteria for each user story and verifies that they are met by the working software. The Product Owner also ensures that the work meets the definition of done, which is a shared understanding of the quality standards for the team3.
1: Government - Building in Quality and Compliance - Scaled Agile Framework 2: Product Owner - Scaled Agile Framework 3: When is a User Story "Done?"- Acceptance Criteria and the Definition of "Done"
[Article] | Treehouse Blog
NEW QUESTION # 26
In a SAFe Roadmap, which PIs are committed?
- A. The first two
- B. All
- C. The first three
- D. The first one
Answer: D
Explanation:
Explanation
According to the Roadmap article on the Scaled Agile Framework website, in a SAFe Roadmap, only the first PI is committed. The article states that "The committed PI shows the results of the teams' most recent PI Planning event where they committed to event the program's PI Objectives. The forecast may provide the deliverables and milestones for the following two PIs." Therefore, the correct answer is A, the first one. The other options are not accurate, as they imply that more than one PI is committed, which is not the case. The roadmap is a forecast, not a guarantee, of future PIs.
NEW QUESTION # 27
What two visual reporting tools can be used to help maintain fiduciary tracking of government technology programs? (Choose two.)
- A. Burn-up charts
- B. Integrated master schedules
- C. Feature progress charts
- D. Detailed spreadsheets
- E. Pro formas
Answer: A,C
Explanation:
Explanation
According to the Government Article on the Scaled Agile Framework website, feature progress charts and burn-up charts are two visual reporting tools that can be used to help maintain fiduciary tracking of government technology programs. The article states that "SAFe provides a wide array of metrics and management tools to monitor program performance. Other metrics-such as feature progress charts, ART Kanban boards, burn-up charts, and continuous flow diagrams (Figure 3)-make program performance highly visible and transparent, enabling better fiduciary control." Therefore, the correct answers are C, feature progress charts, and D, burn-up charts. The other options are not accurate, as they are not the visual reporting tools that can be used to help maintain fiduciary tracking of government technology programs. Detailed spreadsheets (A) are not visual tools, but rather data sources that can be used to create visual reports. Pro formas (B) are financial statements that project future outcomes, not track current performance. Integrated master schedules (E) are traditional project management tools that show the dependencies and milestones of various tasks, not the value delivery and progress of features.
NEW QUESTION # 28
An agency is ready to undertake a large modernization effort. Though the agency ensures the correct implementation of all stage gates in their SDLC, projects seem to always be over budget. They are exploring the use of SAFe due to the success stories from other agencies. What is the appropriate first step?
- A. Identify and train change agents that will lead the effort
- B. Map all stage gates to Agile events
- C. Train Product Owners in the principles, practices, and benefits of adopting SAFe
- D. Start an Agile project with an internal Agile Scrum Master
Answer: A
Explanation:
Explanation
According to the Implementation Roadmap article on the Scaled Agile Framework website, the appropriate first step for an agency that is ready to undertake a large modernization effort using SAFe is to identify and train change agents that will lead the effort. The article states that "The first step in the roadmap is to identify the change agents who will lead the transformation. These are the people who have the vision, influence, and drive to make the change happen. They include executives, managers, coaches, and other leaders who can champion the new way of working and inspire others to follow. Change agents need to be trained in the principles and practices of SAFe, as well as the skills and mindset of Lean-Agile leadership." Therefore, the correct answer is D, identify and train change agents that will lead the effort. The other options are not accurate, as they are not the first steps in the roadmap. Mapping all stage gates to Agile events (A) is a possible activity in the fourth step, which is to create the implementation plan. Training Product Owners in the principles, practices, and benefits of adopting SAFe (B) is a possible activity in the fifth step, which is to prepare for ART launch. Starting an Agile project with an internal Agile Scrum Master is not a recommended step in the roadmap, as it does not involve the whole ART or the Lean Portfolio Management.
NEW QUESTION # 29
What principle from the House of Lean explains the purpose of the PI Planning retrospective?
- A. Relentless improvement
- B. Flow
- C. Innovation
- D. Respect for people and culture
Answer: A
Explanation:
Explanation
According to the House of Lean article on the Scaled Agile Framework website, the principle that explains the purpose of the PI Planning retrospective is relentless improvement. The article states that "Relentless improvement is a constant sense of danger combined with a paranoid desire to find a better way. It's a culture of organizational self-assessment, problem-solving, and action. It's a willingness to change before the crisis forces us to do so. It's a commitment to relentless reflection and a continuous learning journey." Therefore, the correct answer is D, relentless improvement. The other options are not accurate, as they are not the principles that directly relate to the PI Planning retrospective. Respect for people and culture is the foundation of the House of Lean, innovation is the roof, and flow is another principle that supports value delivery.
NEW QUESTION # 30
How does the Incremental Capability Review help streamline execution reviews?
- A. It is the default for phase-gate reviews
- B. It is a document-based progress measure
- C. It is an objective-based progress review
- D. It ensures manual review of processes
Answer: C
Explanation:
Explanation
According to the Adapting Governance Practices to Support Agility and Lean Flow of Value article on the Scaled Agile Framework website, the Incremental Capability Review is an objective-based progress review that replaces the traditional phase-gate reviews. The article states that "The Incremental Capability Review (ICR) is a new governance practice that provides a more effective way to measure progress and manage risk. It is based on the principle of objective evidence of working systems rather than subjective opinions and documentation. The ICR is a lightweight, collaborative, and transparent review process that aligns with the PI cadence and events. It leverages the System Demo, Inspect and Adapt, and PI Planning to provide frequent and incremental checks of the solution's fitness for purpose and compliance with relevant standards and regulations." Therefore, the correct answer is A, it is an objective-based progress review. The other options are not accurate, as the ICR is not the default for phase-gate reviews, it is not a document-based progress measure, and it does not ensure manual review of processes.
NEW QUESTION # 31
In addition to Program Increment (PI) Objectives and uncommitted objectives, what also must be identified during PI Planning?
- A. PI velocity goals
- B. Communication barriers and silos
- C. Program risks
- D. The chain of command
Answer: C
Explanation:
Explanation
In addition to PI objectives and uncommitted objectives, program risks must also be identified during PI planning1. Program risks are the uncertainties or impediments that may affect the ART's ability to deliver value in the PI2. Identifying and managing program risks is a collaborative activity that involves all the teams and stakeholders in the ART. The program risks are captured in the program risks board, which is a visual tool that helps prioritize and track the resolution of the risks3.
1: PI Planning - Scaled Agile Framework 2: Program Risks - Scaled Agile Framework 3: Program Risks Board
- Scaled Agile Framework
NEW QUESTION # 32
What are three reasons the Innovation and Planning (IP) Iteration is critical to success in SAFe? (Choose three.)
- A. It provides a consistent time for PI Planning
- B. It provides the only time the Product Management can conduct backlog refinement
- C. It creates a guard band that ensures program predictability on cadence
- D. It ensures time for creative problem-solving needed by knowledge workers
- E. It is the only way a government ART can afford to do hackathons
- F. It creates a predictable window to allow for personal time off
Answer: A,C,D
Explanation:
Explanation
The Innovation and Planning (IP) Iteration is critical to success in SAFe because it provides the following benefits12:
It creates a guard band that ensures program predictability on cadence. The IP iteration acts as an estimating buffer that helps the ART meet their PI objectives and avoid carrying unfinished work into the next PI.
It ensures time for creative problem-solving needed by knowledge workers. The IP iteration allows the ART to explore innovative ideas, conduct research and design activities, and learn new skills and technologies.
It provides a consistent time for PI Planning. The IP iteration includes time for the PI planning event, which aligns the ART with the vision, roadmap, and strategic themes, and establishes the PI objectives and dependencies.
NEW QUESTION # 33
What events in SAFe provide objective evidence of built-in quality and compliance?
- A. PI Planning
- B. System Demos
- C. ART syncs
- D. Backlog refinement
Answer: B
Explanation:
Explanation
According to the System Demo article on the Scaled Agile Framework website, system demos provide objective evidence of built-in quality and compliance. The article states that "The System Demo is a significant event that provides an integrated view of new Features for the most recent Iteration delivered by all the teams in the Agile Release Train (ART). Each demo gives ART stakeholders an objective measure of progress during a Program Increment (PI). The system demo is part of the inspect and adapt cycle and provides ARTs with the opportunity to assess their current state, adjust, and improve. The system demo also provides feedback on functional and nonfunctional requirements, such as compliance, performance, security, and usability." Therefore, the correct answer is C, system demos. The other options are not accurate, as they are not the events that provide objective evidence of built-in quality and compliance. PI planning (A) is a face-to-face event that serves as the heartbeat of the ART, aligning all the teams on the ART to a shared mission and vision. Backlog refinement (B) is the process of breaking down, estimating, and prioritizing the backlog items. ART syncs (D) are meetings that facilitate cross-team collaboration and alignment.
NEW QUESTION # 34
Which SAFe principle ensures the maximum benefit is generated by understanding trade-offs between risks, cost of delay, operational costs, and development costs for each program and Value Stream?
- A. Build incrementally with fast, integrated learning cycles
- B. Apply systems thinking
- C. Take an economic view
- D. Assume variability, preserve options
Answer: C
Explanation:
Explanation
Taking an economic view is the SAFe principle that ensures the maximum benefit is generated by understanding trade-offs between risks, cost of delay, operational costs, and development costs for each program and value stream1. This principle requires a fundamental understanding of the economics of building systems and making decisions in a proper economic context. This includes the strategy for incremental value delivery and the broader economic framework for each value stream2. Taking an economic view helps to optimize the flow of value, reduce waste, and deliver solutions that meet customer and stakeholder needs3.
1: SAFe Lean-Agile Principles - Scaled Agile Framework 2: Principle #1 - Take an economic view - Scaled Agile Framework 3: Adopting Lean Budgeting Aligned to Development Value Streams
NEW QUESTION # 35
What describes converting unpredictable events into predictable ones?
- A. Innovation and Planning (IP) Iteration
- B. Program Increment (PI) Planning
- C. Cadence
- D. Backlog refinement
Answer: C
Explanation:
Explanation
According to the Apply Cadence, Synchronize with Cross-Domain Planning article on the Scaled Agile Framework website, cadence is the term that describes converting unpredictable events into predictable ones.
The article states that "Cadence is the rhythm, or heartbeat, of the Agile Release Train (ART). It provides a steady and predictable pattern for planning, developing, and delivering value. Cadence helps teams manage the variability inherent in product development. By converting unpredictable events into predictable ones, cadence enables fast and reliable decision-making." Therefore, the correct answer is C, cadence. The other options are not accurate, as they are not the terms that describe converting unpredictable events into predictable ones.
Innovation and Planning (IP) Iteration (A) is a special iteration that occurs at the end of every Program Increment (PI) and provides an opportunity for innovation, planning, and system-level integration and testing.
Program Increment (PI) Planning (B) is a face-to-face event that serves as the heartbeat of the ART, aligning all the teams on the ART to a shared mission and vision. Backlog refinement (D) is the process of breaking down, estimating, and prioritizing the backlog items.