Latest [Mar 28, 2023] PMI PMI-ACP Real Exam Dumps PDF
PMI-ACP Practice Test Questions Updated 210 Questions
The PMI-ACP test evaluates the candidates’ skills and knowledge of Agile principles and techniques. Before starting the preparation process, you should observe the scope of the exam content. All in all, the professionals will encounter the following topics:
- Problem Detection and Resolution
This module contains 5 tasks and comprises about 10% of the exam questions. The students will be required to prove their ability to identify risks, impediments & problems, as well as analyze and determine on time. They also need to have the skills in monitoring and describing the problem resolving status as well as implementing the process changes to prevent them from appearing again.
- Value-Driven Delivery
As for this domain, it contains 4 subdomains and 14 tasks that is about 20% of the exam content. The students need to have the skills in defining the positive value and avoiding the potential downsides as well as possess the knowledge of prioritization & incremental development. Besides that, they have to be good at delivering valuable results by providing high-value increments for review according to the stakeholder priorities and utilizing the stakeholders’ feedback to analyze & develop future increments.
- Continuous Improvement (People, Process, Product)
This is the last topic that has 6 tasks and makes up 9% of the content. The questions from this area validate your competence in improving the value, effectiveness, and quality of the team, process & product.
- Stakeholder Engagement
In the framework of this part, the learners will have 3 subdomains and 9 tasks that comprise 17% of the whole content. They should have an understanding of the stakeholder needs as well as the expertise in ensuring stakeholder involvement & managing the stakeholder expectations. Moreover, you should know the process of engaging the current and future interested companies by creating a trusting environment that adjusts their expectations & needs and coordinates their requests. The individuals should also have the competence in promoting collaboration & participation throughout the project lifecycle as well as providing the tools for informed and effective decision making.
NEW QUESTION 91
Spike solutions are appropriate when:
- A. the business requirements are vague or inadequate for an iteration.
- B. a specific technicalQUESTION NO:needs to be answered, stopping work on the spike as soon as it answers that question.
- C. a technology is understood well and has been used for a while, but needs a problem to be debugged.
- D. there is insufficient time to refactor, but there is a need to resolve a specific problem.
Answer: B
NEW QUESTION 92
Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected. What should the product owner do?
- A. Terminate the project to cut losses.
- B. Continue the project, release the product without the failing feature, and fix the feature in a subsequent release.
- C. Review possible options and make an informed decision to cut losses based on delivered business value.
- D. Bring in experts to increase the probability of success.
Answer: C
NEW QUESTION 93
Extreme Programming (XP) defines four basic activities that are performed during the software development process. These include designing, coding, testing and ...?
- A. Listening
- B. Leveling
- C. Collaborating
- D. Communicating
Answer: A
NEW QUESTION 94
Outing a review session a customer representative is concerned that a story fails to satisfy the scope of work. However the product owner declares that the scope of work is complete What should be done with this story?
- A. Mark it as incomplete and prioritize it for the next sprint
- B. Mark it as complete, since the product owner has the final say
- C. Discard it and create a new story for the remaining scope of work
- D. Mark it as complete, since the team completed the scope of work
Answer: D
NEW QUESTION 95
When does a Sprint get canceled or end early?
- A. When the Sprint backlog is complete
- B. When the Sprint Goal cannot be met
- C. When the definition of "Done" is met
- D. When a key resource is out sick
Answer: B
Explanation:
Explanation/Reference:
NEW QUESTION 96
The Product Owner and Scrum Master are never part of the Development Team.
- A. False
- B. True
Answer: A
NEW QUESTION 97
What should a learn do when they complete ail sprint goals earlier than expected?
- A. Ask the scrum master to select an item from the backlog on which to work
- B. Ask the product owner to select an item from the backlog on which to work
- C. Jointly decide with the scrum master on an item from the backlog on which to work
- D. Begin working on an item in the backlog
Answer: B
NEW QUESTION 98
When are acceptance tests typically written for a user story?
- A. After coding the story, but before user acceptance testing begins
- B. After writing the story, but before coding begins
- C. After estimating the Product Backlog, but before Sprint planning begins
- D. At the start of Product Backlog prioritization planning
Answer: D
Explanation:
Explanation:
NEW QUESTION 99
Following chart lists stories for a release of an Agile project;
If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team's velocity?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
Explanation:
Explanation/Reference:
NEW QUESTION 100
On an Agile team, the project leader works to remove impediments from blocking the team's progress. This is known as what type of leadership?
- A. Servant
- B. Command and control
- C. Consensus-driven
- D. Functional management
Answer: A
NEW QUESTION 101
Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this What should the agile practitioner do?
- A. Ask the product owner to include additional features in the product backlog then replay subsequent iterations
- B. Ask the team to decrease velocity to meet contractual obligations and document this decision
- C. Jointly meet with the team and product owner to discuss options and determine the end date
- D. Announce that the team has exceeded the predicted velocity and that the end date will be earner than planned
Answer: C
NEW QUESTION 102
Who typically has the best insight into task execution?
- A. Team members
- B. Project managers
- C. Agile coaches
- D. Scrum Masters
Answer: A
Explanation:
Explanation
NEW QUESTION 103
During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories. What should the scrum master do?
- A. Create a collaborative team environment so that the team can explore a solution together.
- B. Ask a technical manager or architect to determine a solution to the problem.
- C. Work with the product owner to add a spike to the next sprint to identify a solution.
- D. Ask the lead developer to identify a solution, and then share the details with the team.
Answer: B
NEW QUESTION 104
Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective. What should the agile practitioner do?
- A. Ask team members specific questions to identify the cause.
- B. Encourage the team to continue working to maintain the iteration's schedule.
- C. Review established ground rules with the team.
- D. Meet with the product owner and stakeholders to discuss the issue.
Answer: A
NEW QUESTION 105
Question: Which of the following BEST describes ROTI?
- A. Measure or required effort to complete an iteration
- B. Measure of quality of features delivered in an iteration
- C. Measure of the effectiveness of the retrospective meeting
- D. Measure of product backlog items (PBI) remaining
Answer: C
NEW QUESTION 106
Which of the following drivers is the most important factor in determining the order in which stories will be developed?
- A. Relative cost
- B. Development effort
- C. Customer value
- D. Dependencies
Answer: C
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION 107
Which of the seven principles of software development is best intended to solve the problem of inventories causing hidden errors in the process?
- A. Eliminate Waste
- B. Optimize the Whole
- C. Deliver Early and Often
- D. Fast-Flexible-Flow
Answer: A
Explanation:
Explanation/Reference:
NEW QUESTION 108
What is the definition of velocity?
- A. The number of User Stories in a release
- B. The number of items resolved in a daily Scrum
- C. The number of Sprints per release
- D. The number of story points completed in Sprint
Answer: D
NEW QUESTION 109
During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk.
What should the product owner do now?
- A. Create a spike story to determine what needs to be done to use the new interface.
- B. Lower the epic's priority so that it can be deferred, and analyze it during backlog refinement meetings.
- C. Move the work to the vendor, since they have better knowledge of interface implementation.
- D. Log the risk in the risk register, and share the information with impacted stakeholders at the next monthly review meeting.
Answer: A
NEW QUESTION 110
An Agile team expects a velocity of 8.
During sprint planning, the stories were estimatedand prioritized in the following order:
Story A_4Story Points
Story B_2Story Points
Story C_3 Story Points
Story D_2Story Points
Which stories should the team include in Sprint 1, without splitting the stories?
- A. Stories B, C, and D
- B. Stories A, B, and D
- C. Stories A, C, and D
- D. Stories A, B, and C
Answer: B