NEW QUESTION # 167
How many Scrum Masters are allowed in one Scrum Team?

  • A. 1-2
  • B. As much as needed.
  • C. 0

Answer: C


NEW QUESTION # 168
The Sprint Goal is the single objective for the Sprint.

  • A. TRUE
  • B. FALSE

Answer: A


NEW QUESTION # 169
What happens usually between a Sprint Retrospective and the next Sprint Planning?

  • A. User Story "grooming".
  • B. Product Backlog refinement.
  • C. Nothing!

Answer: C


NEW QUESTION # 170
The Sprint Backlog content is emerging during the Sprint.

  • A. False
  • B. True

Answer: B


NEW QUESTION # 171
Which tasks should take place between two Sprints?

  • A. The Sprint Retrospective.
  • B. Working on the Definition of Done.
  • C. None

Answer: C


NEW QUESTION # 172
Two Scrum Teams are working on the same product. Do they have to share the same Definition of Ready?

  • A. No
  • B. Yes

Answer: A


NEW QUESTION # 173
Items in the Sprint still not meet the Definition of Done .
What should you do as a Scrum Team?

  • A. Do not consider it as a part of the Increment.
  • B. Ask your quality assurance responsible to decide what to do.
  • C. Considert it as a part of the Increment as long it does not break the build.

Answer: A


NEW QUESTION # 174
Which two of the following are correct about the Product Owner accountability (role = outdated term)?

  • A. Answering questions regarding the Product Backlog Items
  • B. Is responsible for maximizing the product value
  • C. Prioritizes the Sprint Backlog

Answer: A,B


NEW QUESTION # 175
Why are smaller teams better, following Scrum?

  • A. Smaller teams are more creative.
  • B. Smaller teams communicate better and are more productive.
  • C. The controlling for smaller teams is much easier.

Answer: B


NEW QUESTION # 176
When n Scrum teams are working on a product, there should always be only 1 Product Owner but 1-n Scrum Masters.

  • A. False
  • B. True

Answer: B


NEW QUESTION # 177
Which answer is correct about the Definition of Done?

  • A. It is defined by the Product Owner.
  • B. It can be improved over time.
  • C. There can be more than one Definition of Done when multiple teams are working on a product (no shared Definition of Done).
  • D. It makes the life of the project manager easier.

Answer: B


NEW QUESTION # 178
Which two questions are answered by the Sprint Planning?

  • A. Who will be the Product Owner in this Sprint?
  • B. What can be delivered in the Increment resulting from the upcoming Sprint?
  • C. How much budget is available in the next Sprint?
  • D. How will the work needed to deliver the Increment be achieved?

Answer: B,D


NEW QUESTION # 179
A baselined Product Backlog is called?

  • A. Release Plan.
  • B. Sprint Backlog.
  • C. The Product Backlog is not baselined.

Answer: C


NEW QUESTION # 180
Where is an evolving environment reflected in Scrum?

  • A. In the Product Backlog.
  • B. In the number of Product Owners assigned to the Team.
  • C. In the Scrum Team salary.

Answer: A


NEW QUESTION # 181
Self-managing teams do not require a Product Owner as they manage the Product Backlog without this accountability.

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 182
The Definition of Ready is defined by the Product Owner.

  • A. False
  • B. True

Answer: A


NEW QUESTION # 183
Developers in a Scrum Team are responsible for holding each other accountable as professionals.

  • A. TRUE
  • B. FALSE

Answer: A


NEW QUESTION # 184
The Product Owner must attend the Daily Scrum?

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 185
Which two of the following are correct about the Scrum Master accountability (role = outdated term)?

  • A. Prioritizes tasks in the Sprint Backlog.
  • B. The Scrum Master decides the number of items for the upcoming Sprint.
  • C. The Scrum Master facilitates the meetings as required or requested.
  • D. The Scrum Master runs the Daily Scrum.
  • E. The Scrum Master removes impediments.

Answer: C,E


NEW QUESTION # 186
Which Scrum Event is timeboxed to a maximum of four hours?

  • A. The Daily Scrum
  • B. The Sprint Retrospective
  • C. The Sprint Planning
  • D. The Sprint Review

Answer: D


NEW QUESTION # 187
Sprint Planning initiates the Sprint by laying out the work to be performed for the Sprint.

  • A. TRUE
  • B. FALSE

Answer: A


NEW QUESTION # 188
The Sprint length can be 6 weeks.

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 189
......


Scrum PSPO-I Exam is a rigorous test that assesses the knowledge and expertise of product owners in various areas, including product strategy, market analysis, user experience design, and agile development practices. PSPO-I exam consists of 80 multiple-choice questions that cover different aspects of product ownership. To pass the exam, candidates must demonstrate a deep understanding of the Scrum framework and its application in product development. Professional Scrum Product Owner I certification is recognized globally and is highly valued by employers who seek professionals with proven skills in product ownership.

 

Quickly and Easily Pass Scrum Exam with PSPO-I real Dumps: https://www.testinsides.top/PSPO-I-dumps-review.html

Realistic PSPO-I Dumps Questions To Gain Brilliant Result: https://drive.google.com/open?id=1tl-DFXqnZdQLZC4eMSVc3f-sETo0Nb7h